Installation⁣⁣⁣⁣⁣

Mounting kit

MONT-KIT-85 | MONT-KIT-85S is supplied with all models by default. It allows to make reliable and easy installation of the unit with two-axis adjustment. Assemble the Mounting kit according to the scheme below. The nut must be tightened until the spring washer clicks, without over-tightening.

Mounting is carried out on a pole with a diameter 30-85 mm. There are also possible options for mounting on a wall or pole with a diameter more than 85 mm.

Cable Gland Assembly⁣⁣⁣⁣⁣⁣⁣

Cable Gland Assembly for RJ-45 connector

Required components are listed below.

  1. Unshielded RJ-45 connector.

  2. Shielded RJ-45 connector.

  3. FTP Cat5e cable.

  4. Cable gland:

    • Cable gland nut.

    • Split sealing grommet (with inner diameter 7 mm).

    • Cable gland threaded coupling.

  5. Crimping tool for RJ-45 connector.

Assemble procedure

In order to ensure that the device case remains sealed under any environmental conditions follow the assemble procedure:

  • Step 1: Crimp the standard RJ-45 connector onto the cable using crimping tool. Pin-out scheme: T568B wiring standard.

  • Step 2: Assemble cable gland nut, the split sealing grommet and the cable gland threaded coupling onto the pre-terminated cable as shown on the figure below.

  • Step 3: Insert the split sealing grommet into the cable gland threaded coupling.

  • Step 4: Insert the RJ-45 connector into the device socket until you hear a click.

  • Step 5: Screw the cable gland threaded coupling into the port and tighten it. Do not apply excessive force.

  • Step 6: Tighten the cable gland nut (4). Do not apply excessive force.

Cable Gland Assembly for Optical Cable

Required components are listed below.

  1. Optical cable.

  2. Optical connector.

  3. SFP module.

  4. Cable gland:

    • Cable gland nut.

    • Split sealing grommet (with inner diameter 3.2 mm).

    • Cable gland threaded coupling.

Assemble procedure

  • Step 1: Put the cable gland nut, the split sealing grommet and cable gland threaded coupling onto the optical cable as shown on the figure below.

  • Step 2: Insert the split sealing grommet into the cable gland threaded coupling.

  • Step 3: Set the SFP module into the socket until you hear a click.

  • Step 4: Insert the optical connector into the SFP module.

  • Step 5: Screw the cable gland threaded coupling into the port and tighten it.

  • Step 6: Tighten the cable gland nut. Do not apply excessive force.

Mounting⁣⁣⁣⁣⁣⁣⁣⁣

Pre-installation

Reqiered tools

  • Screwdriwer set.

  • Pliers / pipe wrench.

  • Wrench set.

Additional equipment

  • GPS receiver.

  • High magnification binoculars.

Installation Procedure

1a. In case of device with removable parabolic antenna, to mount the reflector to Quasar, proceed as follows:

  • Match the antenna reflector with the cover of the outdor unit to coincide the cut parts of the antenna and the slots of the enclosure to prevent rotation of the antenna during operation.

  • Install the sealing metal ring of the feeder on top of the antenna reflector, screw the feeder into the hole to press the reflector to the device enclosure.

  • Tighten the feeder with a 45 mm wrench with a force of 700-800 Nm.

1b. In case of device with external antenna, to mount and connect an external antenna to Quasar, proceed as follows:

  • Mount the antenna(s) according to manufacturer’s instructions;

  • Connect the ODU V and H N-type interfaces to the antenna(s) with RF coaxial cables and with appropriate connectors. Use cables not longer than 3 m (9.8ft). Tighten the N-type connectors to a torque setting of 1.7 Nm (1.3 lb ft);

  • Form drip loops near the cable ends at the ODU’s side so that water doesn’t creep towards the ODU connectors;

  • Weatherproof the N-type connectors (when antenna alignment is complete) using PVC tape and self-amalgamating rubber tape;

  • Weatherproof the antenna connectors in the same way (unless the antenna manufacturer specifies a different method);

  • Fix the antenna cables to the supporting structure using site approved methods. Ensure that no undue strain is placed on the ODU or antenna connectors. Ensure that the cables do not flap in the wind, as flapping cables are prone to damage and induce unwanted vibrations in the supporting structure.

Install ODU connector facing down using the mounting kit. Do not tighten the fasteners to the end until the alignment is completed.

  1. Connect the Cat5e FTP cable with the cable gland to ODU.

  2. Perform ODU grounding.

  3. Lay the Cat5e FTP cable from ODU to the power supply.

  4. Connect the Cat5e FTP cable with a shielded connector covered by a cap to the "OUT" port of the power supply, having previously touched the power supply connector case with FTP cable connector case.

  5. Perform the power supply grounding.

  6. Connect the laptop using Cat5e FTP cable to the power supply "IN" port.

  7. Connect the power cord to the power supply and then to the power circuit.

Make sure a small loop (at least 10 cable diameters) is provided before the Cat5e FTP cable enter into the building.

Grounding and lightning protection⁣⁣⁣⁣⁣⁣⁣⁣

This section describes factors to be considered when planning the proposed link end sites, including grounding, lightning protection and equipment location for the wireless device, power supply, AUX-ODU-LPU-L unit (if installed).

Grounding and lightning protection recommendations

  • The wireless device should be placed on the pole at a height that is at least 1 meter below the top of the pole. In this case, there is a significant probability that the lightning strikes the pole and not the wireless device. The pole should be properly grounded: connected to the building lightning protection circuit according to your local regulations.

  • All equipment must be connected at stabilized and surge protected power sources which must be properly grounded.

  • The end of the FTP service cable that is connected to the power supply should be assembled with a shielded RJ-45 connector. The other end of the FTP service cable (connected to the wireless device) should be assembled with unshielded (standard) RJ-45 connector.

  • The power supply is grounded via a three-conductor power cord and a grounded socket.

  • AUX-ODU-LPU-L and wireless device grounding is performed using grounding bolt.

  • Antenna pole and wireless device should be connected to the common ground ring. Grounding cables should be no less than 10AWG thick and must use corrosion-resistant connectors. Grounding bolt is included in the supply list, M6x10 for BS devices, M5x10 for ST devices.

Requirements to the lightning protection unit AUX-ODU-LPU-L location

AUX-ODU-LPU-L is an optional accessory which may be used to serve as a line protection unit for the ODU and for the indoor network equipment connected to the Ethernet port of the IDU. AUX-ODU-LPU-L should be properly assembled, mounted and grounded.

General recommendations for installations of lightning protection units:

  • Install the lightning protection unit on both ends of the cable to protect both the outdoor and the indoor unit. The purpose of the LPU at the top is to protect the ODU from a surge of lightning strike which can hit the long FTP cable run along the height of the pole or on the roof of the building. The purpose of the LPU at the bottom is to protect the IDU and customer equipment.

  • Use the lightning protection unit to protect all circuits for signal transmission and power supply (video, audio, management signals, Ethernet, etc.)

  • Regularly (especially before the periods with high thunderstorm activity) check the integrity of lightning protection units, grounding elements and bonding conductors.

  • The ports of the AUX-ODU-LPU-L device are symmetrical, i.e. the correspondence of ports position to the external unit and the power supply does not matter.

Make sure to install the two LPU devices as shown in the scheme below.

AUX-ODU-LPU-L Mounting

AUX-ODU-LPU-L is installed on a mast, using clamp. Attach the grounding cable (min cross-section 2.5 mm2) to the case, using grounding bolt. An M6x10 grounding bolt is included in the supply list.

During AUX-ODU-LPU-L mounting it is necessary to provide a small loop of the FTP cable that should be below the cable gland. This ensures that water is not constantly channeled towards the connector. It will also serve as a cable compensation for the cable linear expansion as the temperature difference result.

AUX-ODU-LPU-L Cable Ggland Assembly

In order to ensure that the cable gland remains sealed under any environmental conditions, please, follow the assembly sequence according to the procedure below:

  • Step 1: Insert the sealing insert into the clamping claw.

  • Step 2: Assemble the cable gland by putting the thread-lock sealing nut, clamping claw with sealing insert and body onto the cable as shown on the figure.

  • Step 3: Insert the clamping claw with sealing insert into the body as shown on the figure.

  • Step 4: Crimp the standard RJ-45 connector onto the cable using crimping tool. Pin-out scheme: T568B wiring standards.

  • Step 5: Insert the RJ-45 connector into the corresponding socket until you hear a click.

  • Step 6: Screw the cable gland body into the port and tighten it. Do not apply excessive force.

  • Step 7: Tighten the thread-lock sealing nut. Do not apply excessive force.

Antenna Alignment⁣⁣⁣⁣⁣

General recommendations

  • It is recommended to have two teams prepared for alignment procedure, each team with at least two members: one should take the signal readings and communicate with the remote end, the other should manipulate the antenna.

  • For rough alignment use the azimuth, elevation angle and suspension height from planner tool report.

  • On the device case there is a scale indicating the received signal level. The more often indicator flashes, the better quality of the connection. Blinking indicator shows an intermediate state, the more often indicator is blinking, the higher the connection level.

  • For more accurate alignment, use the alignment tool built into the device web interface.

  • After the initial alignment, the device at the remote side must be fixed. Firstly, the alignment is performed for one device, then for another.

Alignment tool

Use the Alignment tool to point and optimize the antenna in the direction of maximum link signal. The built-in graphical antenna alignment tool displays the signal levels for both devices and both polarizations, this makes an alignment process fast and accurate.

To achieve the best performance, RSSI level current values should be -60 ... -40 dBm.